Adaptation of Fireproofing system

​​Status: Ongoing
Period: 2015-2019

In 2015, a new reservoir was created; in 2018 works were initiated to connect the reservoir to the fireproofing system. 

This action, requested by the competent Authorities, will ensure a higher capacity for the collection of water (from the current 80 cubic metres to 1,200). 

The new reservoir will start working by 2019. Licensing will be subsequently launched, as well as a demolition plan for the former reservoir of the fireproofing system.